What does a feasibility study include? What it tells you, and what it doesn't

Updated 23 October 2026. Written by the architects at blng studio, for small developers, landowners and investors in England.

What is a feasibility study in architecture?

The RIBA Plan of Work 2020 puts feasibility studies at Stage 1, Preparation and Briefing. Its overview says Stage 1 "is about developing the detail of the brief", including "ensuring that the brief can be accommodated on the site". It describes feasibility studies like this:

"Feasibility studies are carried out as part of the briefing process to verify whether a site can accommodate the client's needs, or to test a particular aspect of the brief, allowing the brief to be honed as required."

Two points follow from that, and both are useful when you're commissioning one.

It's a test of the brief, not the start of the design. The RIBA is clear that the design of the building starts at Stage 2. A feasibility study can show several ways a site could work; it doesn't pick a final scheme or draw it in detail.

Its job is to change your mind if it needs to. A good study ends with a decision: go ahead, change the brief, or walk away. If you'd go ahead whatever it says, it isn't worth commissioning.

For a developer looking at a site, the brief is usually some version of "how many homes, of what kind, and how risky is it?" We cover the capacity side of that in How many homes can I build on my land?.

What does a feasibility study include?

Scope varies from practice to practice, so ask for it in writing. A site feasibility study for residential development usually covers six things.

1. The site and its constraints. A site visit and a map of what shapes the site: access, trees, levels, neighbours and their windows, flood risk, heritage designations, easements and services. This sets the land you can actually build on.

2. Planning policy and history. The local plan, any design code or conservation area appraisal, national policy, and the planning history of the site and its neighbours. Past refusals, appeals and approvals nearby often tell you more than policy wording does.

3. Capacity options as massing. Not one answer, but a few: for example, a lower, wider option and a taller, narrower one. Each is a 3D envelope you can see in its context, so you can compare height, bulk and impact on neighbours.

4. Unit mix and areas. For each option, how many homes fit, of what size, and how much floor area goes to stairs, corridors and stores. In England, we check homes against the nationally described space standard (NDSS), which applies where the local plan adopts it.

5. Planning risk, issue by issue. A view of where each option is likely to meet resistance, and why: height, density, design, heritage, neighbours, affordable housing, parking or something specific to the site. The RIBA says feasible options shouldn't be narrowed down at Stage 1, so a rating of each option's risk is more useful than a single recommendation.

6. What to check or commission next. The surveys, specialist reports and advice the options depend on, and in what order. This is often the most practical page in the report.

What a feasibility study covers, and what it leaves to others Two columns. Left, in terracotta with ticks, what a feasibility study tells you: site constraints mapped; planning policy and site history; capacity options as massing; unit mix and areas checked against the nationally described space standard; planning risk issue by issue; and what to check or commission next. Right, in grey with crosses, what it does not give you: planning permission; a valuation of the site; Building Regulations approval; surveys such as ground, tree and ecology surveys; legal advice on title or rights of light; and detailed design of the building. WHAT IT TELLS YOU WHAT IT DOESN'T Site constraints, mapped Planning policy and site history Capacity options, as massing Unit mix and areas against NDSS Planning risk, issue by issue What to check or commission next Planning permission A valuation of the site Building Regulations approval Surveys: ground, trees, ecology Legal advice: title, rights of light Detailed design of the building The right-hand column needs other people: the planning authority, a valuer, building control, surveyors and a solicitor.
What an architect's feasibility study covers, and what it leaves to others. The right-hand column is for planners, valuers, surveyors, building control and solicitors, or for a later design stage.

What a feasibility study doesn't include

Most disappointment with feasibility studies comes from expecting them to answer questions they were never meant to answer. Here's what's outside the scope, and who covers it.

Planning permission. Only the local planning authority can grant it, through a planning application. A feasibility study is a professional view of the risk, not a prediction of the decision. Pre-application advice doesn't settle it either: Planning Practice Guidance says pre-application advice "cannot pre-empt the democratic decision making process or a particular outcome", although it could be a material consideration.

A valuation or viability assessment. A feasibility study by an architect isn't a RICS valuation, and it doesn't replace a formal viability assessment for planning. For those, you'll need a valuer or viability consultant.

Building Regulations approval. A feasibility study should flag the rules that shape the building at this early stage, such as fire safety and staircases, but approval comes later, from building control.

Surveys. Topographical surveys, ground investigations, tree surveys, ecology surveys, flood risk assessments and drainage studies are specialist work. A study tells you which ones you need.

Legal advice. Title, rights of way, restrictive covenants and rights of light are legal questions. A feasibility study can flag a likely rights of light issue; it can't tell you what it means legally. Ask your solicitor.

A daylight and sunlight report. Daylight considerations in a massing study are high level. A formal daylight and sunlight assessment is a separate specialist report.

Detailed design. Floor plans you could build from, elevations, materials and specifications come at RIBA Stages 2 and 3 and beyond. Feasibility massing shows what could fit, not what the building will look like.

None of this makes the study less useful. It's the cheapest point in a project to find out that a site doesn't work, and the study tells you which of those specialist questions you need to answer next.

Feasibility, pre-app and planning: the order of things

It helps to see where a feasibility study sits in the wider process. The RIBA Plan of Work 2020 sets out the planning steps it calls core statutory processes:

From feasibility to a planning application Five steps in a row, following the RIBA Plan of Work 2020. A feasibility study at Stage 1, highlighted in terracotta, asks whether the site can take the brief. Pre-application advice is sourced at Stage 1 and obtained at Stage 2. Concept design at Stage 2 develops the options. Spatial coordination at Stage 3 coordinates the design. A planning application is generally submitted at the end of Stage 3. Below the first step, a terracotta bracket marks the decision the study informs: go ahead, change the brief, or walk away. RIBA PLAN OF WORK 2020, IN ENGLAND Feasibility study RIBA Stage 1 Can the site take the brief? Pre-application advice RIBA Stages 1 to 2 Sourced, then obtained Concept design RIBA Stage 2 Options developed Spatial coordination RIBA Stage 3 Design coordinated Planning application End of RIBA Stage 3 Where it's generally made Your decision point Go ahead, change the brief, or walk away, before you pay for design.
From feasibility to a planning application, following the RIBA Plan of Work 2020. The feasibility study is where you decide whether to carry on, before you pay for design.

What pre-application advice is

Pre-application advice is the council's informal view of a proposal before you apply. Most councils run a paid service with a written response, and often a meeting.

Why feasibility comes first

Pre-application advice is far more useful when you go in with a tested idea. A feasibility study gives you the options, the constraints and the questions to ask: "Would you support five storeys here?" is a better pre-app question than "What can I build?". It also means you go to the council only with options the site can take.

How to read the results

When the report arrives, look for three things.

A range, with reasons. Capacity should come as a range across the options, each with its assumptions stated. A single number with no reasoning is a red flag.

The risks that would change the answer. Which issues could cut the number of homes, or stop the scheme? Which surveys or reports would settle them, and how quickly?

The decision it points to. Go ahead (perhaps to pre-application advice), change the brief (fewer homes, a different mix, a different height), or walk away. A study that leads you to walk away from the wrong site has done its job.

When to commission one, and what to bring

The best time is before you commit: before you exchange on a site, agree a price based on a number of homes, or appoint a full design team. A study can also help if you already own land and want to know whether to apply, or if a scheme has been refused and you want to test a different approach.

It helps to bring:

What a Feasibility Sprint includes

Our Feasibility Sprint is a fixed-scope feasibility study for one site in England, with a fixed fee quoted per site after a free intro call. It includes:

The target delivery is 10 working days from the Start Date. It isn't a valuation, a viability assessment, a daylight report, a planning application or a design appointment.

Frequently asked questions

What does a feasibility study include?

For a residential site, usually a site visit, a constraints map, a review of planning policy and history, a few capacity options as massing, a unit mix and area schedule, a view of the planning risk and a list of what to check next. Ask for the scope in writing, because it varies.

Which RIBA stage is a feasibility study?

RIBA Stage 1, Preparation and Briefing, in the RIBA Plan of Work 2020. Its purpose is to check that the brief can be accommodated on the site. Design starts at Stage 2.

Is a feasibility study the same as pre-application advice?

No. A feasibility study is your own architect's test of the site. Pre-application advice is the council's informal view of a proposal. A study usually comes first, so you go to the council with options worth discussing.

Will a feasibility study get me planning permission?

No. Only the council can grant planning permission, through an application. A feasibility study gives a professional view of the planning risk, and pre-application advice can't pre-empt the decision either.

Do I still need surveys after a feasibility study?

Usually, yes. The study tells you which surveys and specialist reports your options depend on, such as a topographical survey, trees, ecology or flood risk, so you commission the right ones in the right order.

Testing a specific site?

If you're weighing up a site, the Feasibility Sprint tests it before you commit to it: three options, the planning risks, and what to check next. It covers sites in England.

Book a free intro call or see the Feasibility Sprint.